Completed Upper Lift With Reinforcement Exposed Below
The upper section of the retaining wall is fully shotcreted, with reinforcement exposed at the lower lift for the next phase. Work continues downward as excavation and drilling progress along the slope.
Shotcrete Application on Lower Wall Section
Crew members apply shotcrete to the lower lift of the retaining wall. This phased approach stabilizes each section before excavation continues, allowing safe construction on steep terrain.
Soil Nail Bearing Plate Installed on Fresh Shotcrete
Close-up of a soil nail bearing plate set into the shotcrete facing. These plates secure each nail to the wall system, ensuring proper tension and long-term stability as we progress downward through each lift.
Mid-Project Progress - Multi-Lift Wall System
A view of the retaining wall midway through construction, showing completed shotcrete lifts above and reinforcement prepped below. The wall is built in stages to safely support the hillside and maintain structural integrity throughout the process.